morjim toilet
I was on site on monday to review the work:
Besides the workmanship there are several issues:
Ashok tells me that there were certain changes regarding the planter near the WC and tub:
It was eliminated, and certain site decisions were also taken to change positions of WC cubicle etc.
Because of all this, the space to access the tub and shower cube area is not the same, it is much reduced and after glass of shower cube is fitted, one would have only two feet to squeeze through...
There are two aspects in this :
1 There were discrepancies between the written dimensions and the dimensions on site, in which case the contractors should have brought it to our notice before execution
2 According to the contractor there were certain ad-hoc changes including the planter that was specifically meant to create a 1 m clear space for a person to walk thru etc. These changes were informed to us either by client or contractors.
Again the contractor tells us that the final shape for the tub is now approved , I have not seen it nor has a drawing been made, that can avoid further confusion.
The way forward is :
Lets make a detailed drawing once again of whatever changes the client wants.
Only after detailed drawings are finalised, will the contractor undertake work at one shot.
Dont compromise on any redoing of shoddy work on work not as per frozen plans, because any delay is still better than having a bad toilet for life
Let the contractor give a day by day schedule of getting the toilet redone
We will post an engineer on site to monitor the work on site, for the duration of the work.
My office will be mailing a pdf of the original toilet with clearances and distances for your reference
Either ways the way forward